Investor Facilitation Portal

OTHER APPROVALS

Department

Labour and Employment

Checklist

1. Form No. 3
2. Photo I. D. and residence proof of Manager
3. Photo I. D. and residence proof of Occupier
4. List of raw material, finished goods
5. Flow process chart
6. Process description
7. Stability certificate issued by competent person in form No. 1A

Timeline

90 Days

View PDF

Department

Urban Development and Urban Housing Development

Checklist

1. Certificate of registration under Shops & Establishment Act

Timeline

1 Day

View PDF

Department

Labour and Employment

Checklist

1. Previous Certificate

Timeline

15 Days

View PDF

Department

Labour and Employment

Checklist

1. Applicant’s Profile through Online Application:
Profile consists Company Introduction, Manpower details, Work Experience, Products Range, Workshop Production Facilities etc.
???OTHER4_3???
???OTHER4_4???
???OTHER4_5???
???OTHER4_6???

Timeline

30 Days

View PDF

Department

Labour and Employment

Checklist

1. Applicant’s Profile through Online Application:

Timeline

30 Days

View PDF

Department

Labour and Employment

Checklist

1. Applicant’s Profile through Online Application:

Timeline

30 Days

View PDF

Department

Labour and Employment

Checklist

1. Applicant’s Profile through Online Application:
Profile consists Company Introduction, Manpower details, Work Experience, Products Range, Workshop Production Facilities etc.

Timeline

30 Days

View PDF

Department

Labour and Employment

Checklist

1. Work order/Agreement with principal employer (Latest copy of contract or work order)
2. Copy of Old License

Timeline

90 Days

View PDF

Department

Gujarat Pollution Control Board

Checklist

1. Application processing fees for the period of five years with break-up
2. Site plan showing the distance of (NA if the industry is to be located in GIDC estate)
• Nearest residential area with certificate of Talati /Mantri from the proposed site
• Nearest of state/ national highway from the site of the unit/industries
• Nearest Lake/ Pond/ River/ Sea/ Canal/ Forest area and any water body
• Nearest spaces of tourist and historical important
• School, collage, Temple, Mosque etc.
3. Lay Out plan showing the location of the:
• Vents/ Stacks/ Chimney and emission points
• Drainage and final disposal for liquid effluent
• Solid waste collection/ storage/ disposal facility
• Total available open land in the industrial premises
4. List of partner/ Directors (names along with residential address) and telephone number
5. Details of effluent Treatment Plant along with flow diagram
6. Letter of membership of common effluent Treatment plant if applicable
7. Analysis report of Treated and untreated effluent (Air, water and Hazardous solid waste for Schedule II category from Laboratory specified under HW Rules)
8. Break-up of water uses and water balance
9. Details of manufacturing process, with process flow diagram and all chemical equations
10. Environmental statement (form-V)
11. Certificate of SSI. (Compulsory for HW fees)
12. Details of air pollution control measures: stack/ chimney wise for flue gas and process emission
13. Boiler, Steam generating certificate indicating steam generation and consumption of coal tons per day duly certified by office of boiler inspector (in case of IBR Boiler)
14. Compliance regarding public hearing /environmental clearance certificate, if applicable
15. List of raw material with quantity per month (MT/M) (Verify Applicability of CPCB Registration
16. List of product/by-product with quantity per month (MT/M) (Verify Applicability of CPCB Registration for disposal)
17. Copies of consent order /authorization order along with CC&A for which they have last consent
18. C.A. Certificate for project (if SSI unit)
19. C.I. NO. For Dyes
20. Properly filled up Form: I as per Hazardous waste (M&H) amended Rules, 2003.
21. Annual Report in Form-IV (in case of renewal application), with documents of disposal complying Generation, Stock and Disposal justifying stock (Every Year by 31st January)
22. Annual Report in Form 12 in case of recycler/ re-refiner of HW as covered in Schedule 4, 5 and 6 of HW Rules
23. Annual Report in Form 13 in case of Generator or Auctioneer of HW as covered in Schedule 4, 5 and 6 of HW Rules
24. Form-V under Hazardous waste Rules-1989 in case of accident
25. Form-VI & Form-VII in case of important of Hazardous waste under Hazardous waste Rules-1989
26. Photographs of Hazardous Waste Storage facilities
27. Undertaking should be checked as per amended Rules, 2003 – In case of nonapplicability of HW Rules
28. Details of step taken by the applicant for reduction and prevention in the waste generated or for recycling or reuse (Copy of under taking for the same)
29. Membership certificate of common TSDF /Common incinerator (if applicable)
30. Details of HW as per 2003 amended rules or for all categories with Quantity, for Reception (Reprocessor/ Re-cycler), Generation, Collection, Storage, Treatment (Details of Method) and Disposal (Details of Method)
31. Compliance of earlier authorization in case of renewal.
32. Copy of CPCB registration or proof of application made to CPCB in case of recycler/ rerefiner of HW as covered in Schedule 4, 5 and 6 of HW Rules
33. Copy of Inter State Transport NOC under Rule 7(6) in case of Selling/ receiving HW To/From State other than Gujarat
34. Inspection Report in CPCB Performa in case of authorization for registration as recycler/ preprocessor
35. In Case of rejected application compliance of reasons of rejection
36. Form I of Environmental Clearance, if Environmental Clearance is applicable
37. For ground water, central ground water authority permission, if in dark zone

Timeline

120 Days

View PDF

Department

Labour and Employment

Checklist

1. Work order/Agreement with principal employer
2. Copy of Previous license

Timeline

90 Days

View PDF

Department

Food and Drug Controls Administration

Checklist

1. Signed copy of Application Form 19 / Form 19 C/ Form 19 B
2. Signed copy of Additional Information Form
3. True Copy of Partnership deed or Memorandum of Article of Association & List of Directors, if any
4. Appointment Letter of a Registered Pharmacist
5. Consent Letter of a Registered Pharmacist with Details of Previous Service, if any
6. True Copy of Registration Certification issued by Gujarat State Pharmacy Council
7. True Copy of Renewal Receipt of Gujarat State Pharmacy Council as a Proof of Registration of the Pharmacist has been Renewed
8. Passport Size Photographs of the Pharmacists
9. An Affidavit of the Pharmacist on INR 20 Stamp paper
10. True Copy of Rent Receipt for the Premises & Necessary Proof for the Legal Possession of the Premises like Copy of the Registered Sales deed etc.
11. Rough Sketch of the Premises
12. Copy of Ration Card or PAN Card or Identity Card or Aadhar Card of all Partners or Directors & Pharmacist

Timeline

30 Days

View PDF

Department

Food and Drug Controls Administration

Checklist

1. Application in form No.24 and 27 (Signed by all partners and directors)
2. Additional Information Form (Signed by all partners and directors)
3. Authorization letter
4. MOA / partnership Detail/LLP
5. List of Directors along with photo ID
6. Approved plan copy
7. Documents of possession of premises
8. List of technical person with appointment letter, consent letter, degree certificate
9. List of products
10. Additional information form for product (Signed by all partners and directors)
11. Draft label
12. AHU Detail (Air Handling Unit) – Qualification details and Schematic Diagram
13. Water system Detail - Qualification details and Schematic Diagram
14. List of Manufacturing equipment
15. List of laboratory equipment
16. Flow chart
17. List of SOP

Timeline

60 Days

View PDF

Department

FCS - LMD

Checklist

-

Timeline

-

View PDF

-

Department

Food and Civil Supplies

Checklist

1. Last year verification certificate
2. Bill in the case of Manufacturer only

Timeline

07 Days (Verification in Office) 15 Days (Verification Outside Office)

View PDF

Department

Food and Civil Supplies

Checklist

1. Partnership deed/copy of memorandum/full name/father or husband’s name as mentioned in voter’s id card
2. Ownership Document or Rental Document & Copy of House Tax / Copy of Electricity Bill
3. Certificate of Shops & Establishment
4. Type of Weights and Measures to be Manufactured
5. Details of Employees (Skilled, Semiskilled, Unskilled, Specially Trained): Copy of educational qualification, Copy of experience certificate, Affidavit regarding employer mentioning that he will serve for the firm
6. Model approval certificate issued by Government of India
7. Form III-C (Safety Valves Certificates)
8. List or Purchase Bill or Verification Certificate
9. Copy of election card or AADHAR card
10. Copy of PAN card

Timeline

50 Days

View PDF

Department

Food and Civil Supplies

Checklist

1. Partnership deed/copy of memorandum/full name/father or husband’s name as mentioned in voter’s id card
2. Ownership Document or Rental Document &Copy of House Tax / Copy of Electricity Bill
3. Certificate of Shops & Establishment
4. Type of Weights and Measures to be Manufactured
5. Copy of election card or AADHAR card
6. Copy of PAN card

Timeline

20 Days

View PDF

Department

Food and Civil Supplies

Checklist

1. Partnership deed/copy of memorandum/full name/father or husband’s name as mentioned in voter’s id card
2. Ownership Document or Rental Document &Copy of House Tax / Copy of Electricity Bill
3. Certificate of Shops & Establishment
4. Type of Weights and Measures to be Manufactured
5. Details of Employees (Skilled, Semiskilled, Unskilled, Specially Trained): Copy of educational qualification, Copy of experience certificate, Affidavit regarding employer mentioning that he will serve for the firm
6. Purchase bill/Verification Certificate
7. List or Purchase Bill or Verification Certificate
8. Copy of election card or AADHAR card
9. Copy of PAN card

Timeline

35 Days

View PDF

Department

Food and Civil Supplies

Checklist

1. Partnership deed/copy of memorandum/full name/father or husband’s name as mentioned in voter’s id card
2. Ownership Document or Rental Document &Copy of House Tax / Copy of Electricity Bill
3. Certificate of Shops & Establishment
4. Type of Weights and Measures to be Manufactured
5. Details of Employees (Skilled, Semiskilled, Unskilled, Specially Trained): Copy of educational qualification, Copy of experience certificate, Affidavit regarding employer mentioning that he will serve for the firm
6. Model approval certificate issued by Government of India
7. List or Purchase Bill or Verification Certificate
8. Copy of election card or AADHAR card
9. Copy of PAN card

Timeline

35 Days

View PDF

Department

Food and Civil Supplies

Checklist

1. Partnership deed/copy of memorandum/full name/father or husband’s name as mentioned in voter’s id card
2. Ownership Document or Rental Document &Copy of House Tax / Copy of Electricity Bill
3. Certificate of Shops & Establishment
4. Type of Weights and Measures to be Manufactured
5. Copy of election card or AADHAR card
6. Copy of PAN card

Timeline

20 Days

View PDF

Department

Food and Civil Supplies

Checklist

1. Partnership deed/copy of memorandum/full name/father or husband’s name as mentioned in voter’s id card
2. Ownership Document or Rental Document &Copy of House Tax / Copy of Electricity Bill
3. Certificate of Shops & Establishment
4. Type of Weights and Measures to be Manufactured
5. Details of Employees (Skilled, Semiskilled, Unskilled, Specially Trained): Copy of educational qualification, Copy of experience certificate,
Affidavit regarding employer mentioning that he will serve for the firm
6. Purchase bill/Verification Certificate
7. List or Purchase Bill or Verification Certificate
8. Copy of election card or AADHAR card

Timeline

35 Days

View PDF

Department

Road and Building Department

Checklist

1. Identity Proof of Applicant

2. Layout Plan

3. License Agreement for OFC Cable

4. Cross Section of Pipe

5. Address Proof

Timeline

Granting road cutting permission - Seven (7) days, Issuance of restoration certificate - 10 days

View PDF

Department

Commercial Tax

Checklist

???OTHER22_1???
2. Accounting records
3. Details of employees
4. Details of paid salaries
5. Address proof

Timeline

1 Days

View PDF

Department

Food and Civil Supplies

Checklist

1. Document of Premises
2. Empty wrapper/ label inspection report

Timeline

20 Days

View PDF

Department

FCS - LMD

Checklist

-

Timeline

-

View PDF

-

Department

Food and Civil Supplies

Checklist

1. PCR Registration Certificate

Timeline

7 Days

View PDF

Department

IMD-IC

Checklist

1. Printed Copy of online Application form along with Annexure 1 & 2 regardingland duly signed & Stamped.

2. Notarized Affidavit in original as per format.

3. Acknowledgement or registration of Activity of Applicant Unit. (i.e UAN, EM-I,EM-II, IEM, LOI, LOP)

4. Document for Constitution of Applicant/Comapny.

5. Village Map showing survey Nos. applied for.

6. Detailed Lay out plan along with proposed built up Area, Area table and Key Plan.

7. Justification Note for land requirement.

8. Copy of latest. 7/12, 8.

9. Project Report.

Timeline

60 Days

View PDF

Department

IMD-IC

Checklist

1. Application form signed by Authorized Signatory.

2. GST Certificate.

3. Copy of Last year balance sheet or annual report.

4. Copy of Constitution registration.

5. Production and Sales details of last three years.

6. Last three years income tax returns.

7. Copy of Udhyog Aadhaar/EM II/SIA.

8. Copy of licence under Factories Act or Other (if Applicable).

9. C A Certified list of Plant and Machinery with original purchased Value.

10. Last Electricity bill.

11. Copy of NSIC registration (if applicable).

12. Authority Letter of Authorized person/Board resolution/Power of Attorney.

Timeline

60 Days

View PDF

Department

IMD-IC

Checklist

1. Stock Statement from Prohibition & Excise Dept.

2. Details of Current Stock, Production & Sale of Unit.

3. Purpose for which Unit want to Export.

4. NOC of the Export Commissioner of State/UT to which Unit Exports (if Applicable).

5. GPCB CCA/NOC (if Applicable).

Timeline

45 Days

View PDF

Department

IMD-IC

Checklist

1. Name & Residential Address of Proprietary / Partners / Directors of the Enterprise.

2. List of Plant & Machinery .

3. Copy of License of Molasses held previously. Declaration, if such Molasses License is not held (In Case of Existing / Expansion Enterprise).

4. Copy of VAT/CST Registration.

5. Copy of Acknowledgement EM Part – I, EM Part – II, Udhyog Aadhar, IEM, LOI,LOP as the case may be.

6. Month wise details of main Raw Material Purchased & Utilization for Last Two (2) Year Period (In Case of Existing / Expansion).

7. Evidence of Power Connection & Consent Letter, if Power Connection in other’s name.

8. Copy of Consent to Establish (CTE) / Consent to Operate (CTO) from GPCB(Not Applicable in case of Pit Furnace and Induction Furnace).

9. Copy of Shop & Establishment Act Registration, in case of Municipal Area.

10.Details of Molding Area (Not Applicable in case of Induction Furnace).

11.Inspection Required for Additional Requirement of Molasses in case of Expansion and Opinion of Inspector and/or General Manager (GM – DIC) in this Regards.

12.In case of Expansion and Enterprise holding Molasses License, Details of Consumption of Molasses for Last Two (2) Years – Month wise.

13.In case of Expansion, Details of Production for Last Two (2) Years – Month wise.

14.In case of Expansion, List of Additional Plant & Machinery Installed.

Timeline

90 Days

View PDF

Department

IMD-IC

Checklist

1. Stock Statement from Prohibition & Excise Dept.

2. Details of Current Stock, Production & Sale of Unit.

3. Purpose for which Unit want to Export.

4. NOC of the Export Commissioner of State/UT to which Unit Exports (if Applicable).

5. GPCB CCA/NOC (if Applicable).

Timeline

45 Days

View PDF

Department

IMD-IC

Checklist

1. Process description with chemical reaction.

2. Flow sheet.

3. Material balance for one batch & batch timing.

4. Theoretical requirement of alcohol per Kg. product.

5. Recycling of waste stream containing alcohol.

6. Possibility of recovery of alcohol from waste stream/vents.

7. Any other solvents tried in place of alcohol, if yes, details of results obtained.

8. Detail list of proposed machinery with its capacities.

9. A copy of EM - I / EM - II / Udhyog Aadhar / IEM Registration/Industrial License/Letter of Intent of the unit.

10.Kind of Spirit and name of denaturant with proportional percentage.

11.If, application is of expansion please give annual capacity before expansion and after expansion, also a list of existing machinery and proposed machinery.

12.If unit is holding valid approval of production programme than details of each programme should be attached and detail progress report.

13.Production of alcohol consuming items and consumption of alcohol for last three years(If the application for expansion purpose).

14.CTE/CTO/CCA from Gujarat Pollution Control Board, Gandhinagar.

Timeline

90 Days

View PDF

Department

IMD-IC

Checklist

1. Copy of EM-II/Udhyog Aadhaar/IEM/LOP/IL (if applicable).

2. GPCB consent / Environment Clearance from MOEF/Authorization from CPCB.

3. Annual production Capacity and Item Wise Production Capacity.

4. List of Product with specification number and equipment list as per B.I.S.

5. Test Report last three batch as per B.I.S Specification (if available).

6. Details of Technical Staff (with name and Education Qualification).

7. Process Chart of each produced Item.

8. Bills of Plant & Machinery.

9. Bills of Laboratory Equipment.

10.Proof of Three Phase Connection.

11.Copy of License issued by DIC, in case of Renewal.

12.Reports from Food and civil Supply department of last 5 years, in case of renewal.

13.Details of Production, Sale and Purchase, in case of renewal.

Timeline

90 Days

View PDF

Department

IMD-IC

Checklist

1. Application form duly signed & Stamped by Authorized person.

2. Copy of constitution of applicant (partnership deed/ Memorandum of Article/ registrar of firms etc.).

3. Constitution of Enterprise.

4. Specifications of Products for Oil & grease given by Authorized Dealer.

5. Certificate from Authorized Dealer.

6. Proof of Land (N.A. Permission, Land Purchase Deed, Rent Deed etc.)

7. Certificate of G.S.T.

8. Udyog Aadhaar Memorandum (if Applicable).

9. Explosive License (in case of Petrol Pump).

10.License for Essential Commodities.

11.Proof of Identity of Proprietor/Partners.

12.Copy of Previous License (In case of Renewal).

13.Purchase Bill (In case of Renewal.

14.sale Bill (In case of Renewal).

15.Details of Purchase & Sale of Last Six months (In case of Renewal).

Timeline

90 Days

View PDF

Department

Energy and Petrochemicals Department (EPD)

Checklist

1. Overall Single Line Diagram showing existing and proposed installations

2. Equipment Layout Drawing with plot plan

3. Earthing layout drawing with Standard Earth Pit Drawing

4. Details of DG in prescribed format with declaration

5. Purchase Invoice, Load List, Copy of the Electricity Bill, OR in case of estimate from DISCOM

6. In case of U/G cable, details of the Cable Duct and Cross-section of the Cable

Timeline

15 Days

View PDF

Department

Gujarat Pollution Control Board

Checklist

As per attached file

Timeline

90 Days

View PDF

Department

Gujarat Pollution Control Board

Checklist

As per attached file

Timeline

90 Days

View PDF

Department

Tourism Department

Checklist

1. Brief Synopsis (min. 500 words)
2. Cover Letter
3. Identity Proof
4. Script, if applicable
5. Authorisation letter in favour of person filling the application, if applicable 6. In case of international project/applicant, valid visa copy/authorization letter

Timeline

7 Days

View PDF

Department

Urban Development and Urban Housing

Checklist

High rise building:
1. Lift Certificate
2. Annual Maintenance Contract Agreement (AMC)
3. Building Drawing
4. Video and Photographs of the site
5. Fire Fighting Equipment Photographs
6. Test Certificate of Fire Equipment
Low rise building:
1. Lift Certificate
2. Building Drawing
3. Fire Fighting Equipment Photographs
4. Test Certificate of Fire Equipmen

Timeline

7 Days

View PDF

Department

Home Department

Checklist

1. Applicant ID Proof

Timeline

10 Days

View PDF

Department

Urban Development and Urban Housing Department

Checklist

1. Photograph of Applicant
2. PAN Card of Applicant
3. Aadhar Card of Applicant
4. Property Tax Bill of organization for address proof
5. Rent Agreement (if property on Rent)
6. Owner's Aadhar Card or residence address proof
7. Bill Copy or Establishment letter pad or Establishment PAN Card or GST No.
8. Partnership Agreement copy - if partnership firm
9. Memorandum of the Companies Act 2013 or Certificate of RBI or Registration Certificate of Ministry of Corporate Affairs
10. Service Provider Agreement
11. Owner Photograph
12. Photocopy of Gumasta

Timeline

1 Days

View PDF

Department

Urban Development and Urban Housing Department

Checklist

1. Standing Advisory Committee on Radio Frequency Allocation (SACFA) permission letter / Receipt of Application done with SACFA
2. Airport Authority of India NOC (If applicable)
3. National monument Authority NOC (If applicable)
4. Agreement between the landlord/owner and the cellular company
5. Receipt of Advance 1-year property tax
6. If tower on existing building:
-Structural Design of existing building
-Soil Testing Report
-Tower Structural Design
-Structural Stability certificate (Proposed Tower + Building)
7. If tower on land:
-Soil Testing Report
-Details of the structural design of the proposed tower
-Certificate of structural stability of the proposed tower

Timeline

30 Days

View PDF

Department

Information and Broadcasting Department

Checklist

Non-mandatory documents:
1. Site plan of the building
2. Character Certificate
3. License for the commercial use of Video/Television under the Indian Telegraph Act 1885 (No. 13 of 1885)
4. Ownership proof of the place
5. Other details Regarding Building

Timeline

30 Days

View PDF

Department

Information and Broadcasting Department

Checklist

1. Copy of old license

Timeline

30 Days

View PDF

Department

Information and Broadcasting Department

Checklist

Timeline

30 Days

View PDF

Department

Information and Broadcasting Department

Checklist

1. Copy of old license

Timeline

30 Days

View PDF

Department

Urban Development and Urban Housing Department

Checklist

1. Affidavit of Road Cutting

Timeline

07 days for application scrutiny and 03 days for inspection

View PDF

Department

Roads and building Department

Checklist

1. Scanned copy of Pan Card, Aadhar Card & GST Registration of applicant

2. Bank solvency document

3. Narmada Bonds

4. Turnover for last 3 years certified by CA

5. Completed Work proof -3A (For upgradation please upload proof of Two/Three works of 50% of maximum financial limits of existing class)

6. Private completed work proof (Form 26-AS & form 3-A certified by CA)

7. Letter of approval from competent authority in case of sublet work

8. Work on hand - Form 3

9. List of tools, plant and machineries (Form 3B)

10. Degree/Diploma Certificate of employed engineer

11. Birth Certificate of employed engineer

12. Aadhar Card of employed engineer

13. Affidavit of employed engineer as per specimen on stamp paper of Rs. 100

14. Proprietor Affidavit of Contractor status

15. Partnership deed of Contractor status

16. Registration of firm of Contractor status

17. Memorandum of association of Contractor status

18. Articles of associations of Contractor status

19. Registration of new firm regarding Registration of sister concern

20. Application form PDF duly signed and stamped by the applicant

Timeline

30 to 60 days (depending upon the class)

View PDF

Department

Gujarat Pollution Control Board

Checklist

As per attached file

Timeline

90 Days

View PDF

Department

IMD-IC

Checklist

Timeline

90 Days

View PDF

Department

Gujarat Pollution Control Board

Checklist

As per attached file

Timeline

90 Days

View PDF

Department

Gujarat Pollution Control Board

Checklist

As per attached file

Timeline

60 Days

View PDF

Department

Gujarat Pollution Control Board

Checklist

As per attached file

Timeline

90 Days

View PDF

Department

Gujarat Pollution Control Board

Checklist

As per attached file

Timeline

90 Days

View PDF